Year in Review Reports
The annual Year in Review reports highlight the major milestones for the Richmond Hill Centre high-density Transit Oriented Community (TOC).
Learn more about Richmond Hill Centre and how we are Thinking Forward.
In 2025 Richmond Hill Centre major milestones included:
- Metrolinx awarded tunnel contract to North End Connectors Consortium for twin 6.3 km tunnels which will run from south of Langstaff Road in Markham to Finch Station
- Zoning initiative for Richmond Hill Centre completed and incorporated into the City’s new Comprehensive Zoning By-law
- Initiated planning for the integration of municipal community facilities into Richmond Hill Centre
- Completed all utility works required for subway tunnel construction
Click below to see full 2025 Richmond Hill Centre Year in Review Report.
2025 Richmond Hill Centre Year in Review Report
In 2024 Richmond Hill Centre major milestones included:
- Metrolinx opened a Community Engagement Office at 295 High Tech Road, to provide direct access for public inquiries, updates and stakeholder engagement.
- City of Richmond Hill updated the Richmond Hill Centre development application process and review.
- Planning, design and relocation of utilities continued in preparation for major construction.
Click below to see full 2024 Richmond Hill Centre Year in Review Report.
2024 Richmond Hill Centre Year in Review Report
In 2023 Richmond Hill Centre major milestones included:
- Council adopts RHCSP
- York Region Council approves RHCSP
- Province advances procurement for YNSE tunneling contract
Click below to see full 2023 Richmond Hill Centre Year in Review Report.