Capital Projects
A capital project is a large-scale project that helps maintain or improve a City asset, often called infrastructure.
The City's capital projects are implemented based on the approved Capital Budget.
Improvements to City Infrastructure and Parks
Richmond Hill is responsible for improving and maintaining existing infrastructure, including buildings, roads, bridges, sidewalks, watermains, sanitary sewers, storm sewers, stormwater management ponds and street lighting, as well as parks and trails.
Watermains and sewers
| Bayview Avenue Watermain Replacement |
|
The City is undertaking the detailed design for the watermain replacement on Bayview Avenue from Elgin Mills Road East to Centre Street East. The scope of work includes the replacement of the existing watermain, valve chambers and fire hydrants along Bayview Avenue. Construction is planned for 2027, subject to future budget approval. For more information, email Project Manager, Anita Wong or call her at 905-771-5461. |
| Enford Road and Industrial Road Watermain and Culverts Replacement |
|
The City is undertaking the detailed design for the watermain and culverts replacement on Enford Road from Elgin Mills Road to Cul-de-Sac and Industrial Road from Yonge Street to Canadian National Railway (CNR). The scope of work may include watermain replacement and its associated appurtenances, sanitary sewers replacement, culverts replacement and carrying out the necessary associated road works. The construction is planned for 2026/2027, subject to the future budget approval. For more information, email Project Manager, Carrie Park or call her at 905-747-6327. |
Roads
| Arnold Crescent, Highland Lane and Elizabeth Street Reconstruction |
|
The City has completed the detailed design for the reconstruction of the following areas:
The scope of work includes:
Construction commenced in November 2025. The underground work will be completed in multiple phases. For further details, please refer to the Phasing Plan.
Construction Updates The Contractor is commenced mobilization on site to install the sanitary sewer by drilling beneath Major Mackenzie Drive along Arnold Crescent, between Guinevere Court and Hopkins Street, began in late March 2026 and continuing through May. Majority of tree removals was completed in the area. Upon completion of these activities, underground works, including watermain, sanitary sewer, and storm sewer installation are scheduled to proceed from April through December 2026. Please be advised that partial lane closures and traffic delays will occur. Temporary traffic diversions may be necessary at certain times to facilitate construction activities safely and efficiently. Road Closures April 13, 2026 to December 2026: Direct Underground Inc. will close Arnold Crescent between Major Mackenzie Drive and Elizabeth Street to install new underground infrastructure, including watermains, sanitary sewers, and storm sewers, all aimed at improving safety for both the public and workers. During this closure, emergency vehicles and local traffic within the restricted area will still be able to access Arnold Crescent. All other vehicles must use detours on Major Mackenzie Drive, Elizabeth Street, Centre Street, Yonge Street, and the sections of Arnold Crescent that remain open. Waste Collection During Road Closure April 27, 2026 to December 2026: The waste collection contractor, Miller Waste, will continue to provide waste collection for residents within the construction area. Effective the week of April 27, 2026, waste collection will begin as early as 7:00 a.m. and will remain in effect until the road is reopened. This adjustment is necessary to accommodate the construction schedule.
We appreciate your understanding and cooperation as construction progresses while essential City services remain operational. For any questions related to waste collection, please reach out to Access Richmond Hill at access@richmondhill.ca or 905-771-8800. Additional Information
For additional information, email Project Manager, Carrie Park or call her at 905-747-6327. |
|
Bantry Avenue and Briggs Avenue Active Transportation Improvements |
|
The City is undertaking a Feasibility Study for Active Transportation improvements along Bantry Avenue and Briggs Avenue, from Yonge Street to Blackmore Avenue. The Feasibility Study commenced in summer 2023 and work is on-going. Public Information Centre A Public Information Centre was held at the Langstaff Community Centre (Yorkshire Room) on Thursday May 16, 2024 which featured a hybrid presentation (available in-person and online) and an open-house style session for in-person attendees. The presented materials can be viewed at the link below: Thank you to all residents who attended the public meeting or submitted comments to the City. Next Steps The preferred concept design will be further developed through detailed design in 2025. Construction is tentatively scheduled for 2027. For more information, email Sustainable Transportation Coordinator, Jennie Geleff, or call her at 647-226-0215. |
| Bayview Park Lane, Sandbanks Drive and Park Crescent Active Transportation Improvements |
|
The City is undertaking the design and construction of active transportation improvements for Bayview Park Lane from Bayview Avenue to Sunset Beach Road, Sandbanks Drive from Bayview Park Lane to Nantucket Drive, and Park Crescent from Nantucket Drive to Sunset Beach Road. The design commenced in summer 2023 and works are on-going. A Public Information Centre was held at the Oak Ridges Community Centre on October 11, 2023. The presentation materials are available for viewing. Thank you to all residents who attended the public meeting or submitted comments to the City. Preliminary designs were developed taking into account site context, historical data, site observations, comments received and relevant policies within Richmond Hill. Implementation has begun, to be completed during summer 2024. For more information, email Sustainable Transportation Coordinator, Jennie Geleff, or call her at 647-226-0215. |
| Blackforest Drive, Acorn Road and Rosegarden Crescent Reconstruction |
|
The City completed the detailed design for the reconstruction of (1) Blackforest Drive from Yonge Street to Greyfriars Avenue, (2) Acorn Road from Blackforest Drive to the south limit, and (3) Rosegarden Crescent in early 2024. The scope of work includes removal of ditches and culverts, boulevard regrading, pavement reconstruction, new curb and gutter, new sidewalks, watermain replacement, new storm sewer system, sanitary sewer upgrade, and streetlight upgrade. Construction started in June 2024, with the first phase focusing on the reconstruction of Blackforest Drive and Acorn Road. The majority of road improvements on Blackforest Drive and Acorn Road were completed in 2024. Remaining work, including streetlight upgrade, sidewalk installation, and driveway paving, was scheduled for spring and summer 2025. The second phase of construction focuses on the reconstruction of Rosegarden Crescent, which began in April 2025. The overall construction project was substantially completed in December 2025. Construction Updates
Public Notices
For more information, email Project Manager, Anita Wong or call her at 905-771-5461. |
| Centre Street East Rehabilitation |
|
The City is currently undertaking the detailed design for the rehabilitation of Centre Street East from Pugsley Avenue to Canadian National Railway (CNR). The scope of the work may include rehabilitation of the road, sidewalk, curb and gutter, as well as the replacement of storm and sanitary sewers as necessary. Furthermore, the City is undertaking the detailed design for the watermain replacement on Centre Street East from CNR to Bayview Avenue. The scope of work may include replacement of watermain and associated appurtenances, water services, hydrants, valve chambers and associated road restoration works. In addition, the scope of work may include the replacement of storm and sanitary sewers as necessary. The construction is planned for 2026/2027, subject to the future budget approval. For more information, email Project Manager, Carrie Park or call her at 905-747-6327. |
|
Coons Road Reconstruction |
|
The City is undertaking the detailed design for the reconstruction of Coons Road from Humberland Drive to Aubrietia Court. The scope of work includes removal of ditches and culverts, boulevard regrading, pavement reconstruction, new curb and gutter, new sidewalks, watermain replacement, new storm sewer system, sanitary sewer repair as required and streetlight upgrade. The design and field investigations commenced in spring 2024. Construction is tentatively planned for 2027, subject to future budget approval. Submit comments regarding the Coons Road design. Additional Information
Public notices For more information, email Project Manager, Kyle Paterson or call him at 905-747-6341. |
| Elm Grove Avenue Reconstruction |
|
The City is undertaking the detailed design for the reconstruction of Elm Grove Avenue from Yonge Street to Parker Avenue. The scope of work includes removal of ditches and culverts, boulevard regrading, pavement reconstruction, new curb and gutter, new sidewalks, watermain replacement, new storm sewer system, sanitary sewer repair as required and streetlight upgrade. The design and field investigations commenced in summer 2023, however the project is currently paused until a drainage study covering the broader area is completed in 2026. Construction is tentatively planned for 2029, subject to future budget approval. For more information, email Project Manager, Anita Wong or call her at 905-771-5461. |
|
Fergus Avenue, Moray Avenue, Olde Bayview Avenue, Capelle Street Reconstruction |
|
The City is undertaking the detailed design for the reconstruction of Fergus Avenue, Moray Avenue, Olde Bayview Avenue and Capelle Street. The scope of work involves the reconstruction of the existing roads, installation of new asphalt pavement, replacement of the watermain, sanitary upgrades, and improvements to streetlights. Construction is planned for 2028, subject to future budget approval. For more information, email Project Manager, Amchan Natkunarajah or call him at 905-771-9996.
Public notices |
| Maple Grove Avenue and Wendy Way Reconstruction |
|
The City is undertaking the detailed design for the reconstruction of Maple Grove Avenue and Wendy Way. The scope of work includes removal of ditches and culverts, boulevard regrading, pavement reconstruction, new curb and gutter, new sidewalk, watermain replacement, new storm sewer system, sanitary sewer repair as required and streetlight upgrade. Construction is expected to start in early 2026. Public notices
For more information, email Project Manager, Kyle Paterson or call him at 905-747-6341 |
| Ohio Road Reconstruction |
|
The City is undertaking the detailed design for the reconstruction of Ohio Road from Elgin Mills Road to the south limit. The scope of work includes removal/regrading of ditches and culverts, boulevard regrading, pavement reconstruction, new curb and gutter, new sidewalk, watermain replacement, new storm sewer system, sanitary sewer repair as required, and streetlight upgrade. The design and field investigations commenced in summer 2023 and the works are on-going. The preliminary design was posted for review, and an online comment form was provided for public input in February 2025. Construction is planned for 2027, subject to future budget approval. For more information, email Project Manager, Anita Wong or call her at 905-771-5461. |
| Red Maple Road Improvements |
|
The City is undertaking the detailed design for Red Maple Road Improvements from High Tech Road to Highway 7. The scope of work includes installation of new traffic signals at the intersection of Red Maple Road and the south driveway of 50 Red Maple Road, and minor modifications to the curb alignment and pavement markings. Construction is planned for 2027, subject to future budget approval. For more information, email Project Manager, Anita Wong or call her at 905-771-5461. |
| Schomberg Road and Aubrey Avenue Reconstruction |
|
The City is undertaking the detailed design for the reconstruction of Schomberg Road (from Maple Grove Avenue to King Road) and Aubrey Avenue (from Schomberg Road to Yonge Street). The scope of work includes removal of ditches and driveway culverts, boulevard regrading, pavement reconstruction, new curb and gutter, new sidewalks, new storm sewer system, watermain replacement, sanitary sewer upgrade, and streetlight upgrade. The Schomberg Road culvert crossing located between Aubrey Avenue and George Street will also be replaced as part of the road reconstruction. The design and field investigations commenced in early 2024 and the works are on-going. Construction is planned for 2028, subject to future budget approval. For more information, email Project Manager, Anita Wong or call her at 905-771-5461. |
|
Valleymede Drive Southbound Right Turn Lane at Highway 7 |
|
The City has completed the detailed design for the construction of a southbound right turn lane at the intersection of Valleymede Drive and Highway 7. The scope of work includes removal of existing infrastructure, utilities relocation, installation of new pavement, replacement of curb and gutter, replacement of sidewalk and restoration of all disturbed areas. Construction is scheduled for Spring to Summer 2026. Transit Impacts The York Region Transit (YRT) bus stop will be permanently relocated from Valleymede Drive, north of Highway 7, to Times Avenue, south of Highway 7. Please contact YRT directly regarding bus stops and bus services. For more information, email Project Manager, Hermie Cheung or call her at 905-771-9996, ext. 5561 |
|
West Beaver Creek Road and West Pearce Street Intersection Improvements |
|
The City completed the detailed design for the proposed traffic signals at the West Beaver Creek Road and West Pearce Street intersection. The scope of work includes installation of new traffic signal conduits and equipment, pavement markings and signage, and minor road widening on West Pearce Street. Construction is expected to start in summer 2026. For more information, email Project Manager, Sebouh Apigian or call him at 905-747-6342. |
|
Teefy Avenue, Moodie Drive, Tennison Road, Jenkins Drive, Udine Court Reconstruction |
|
The City is undertaking the detailed design for the replacement of the watermain on Teefy Avenue, Moodie Drive, Tennison Road, Jenkins Drive and Udine Court. The scope of work may include removal and replacement of curb and gutter, new asphalt pavement, watermain replacement, sanitary and storm sewer upgrades and streetlight improvements. Detailed design is scheduled to commence in 2026. The anticipated construction commencement is scheduled to begin in 2029, subject to future budget approval. For more information, email Project Manager, Amchan Natkunarajah or call him at 905-771-9996.
Public notices |
|
Trench Street Traffic Signals and Traffic Equipment Replacements |
|
The City is undertaking the detailed design for the proposed traffic signals on Trench Street approximately 300 m north of Major Mackenzie Drive West. The scope of work includes installation of new traffic signal conduits and equipment, pavement markings and signage, lighting improvements on Trench Street. Construction is expected to be completed in 2026. For more information, email Project Manager, Amchan Natkunarajah or call him at 905-771-9996. |
|
2025 Sidewalk, Illumination and Pedestrian Crossover (PXO) Program |
|
The City of Richmond Hill is dedicated to maintaining a high-quality sidewalk network and ensuring pedestrian safety. Currently, the City is undertaking detailed design for the following locations:
Construction is expected to start in summer 2026. Public Notices For more information, email Project Manager, Anita Wong or call her at 905-771-5461. |
Bridge and Culvert Rehabilitation
|
Pemberton Road, Walmer Road, Mural Street and Vogell Road Culvert and Storm Structure Rehabilitation |
|
The City has completed the detailed design for the culvert and storm structure rehabilitation at the following locations:
The scope of work includes the installation of environmental protection, structural repairs including culvert liners and concrete patching repairs, and the restoration of all disturbed areas. Construction is scheduled for Spring to Fall 2026. For more information, email Project Manager, Hermie Cheung or call her at 905-771-9996, ext. 5561 |
|
Upcoming Projects |
|
The City is undertaking the detailed design for the rehabilitation of culverts and bridges at various locations within the City. The rehabilitation works are essential to maintain and extend the service life of the City infrastructures. Bridges are structures that provide a safe passage and contributes to the seamless mobility of pedestrians and vehicles across an obstruction or a gap. Culverts are crucial infrastructure that allow for the conveyance of water or the passage of wildlife under a roadway or a pathway. Rehabilitation works could involve embankments and structure components repairs to replacement of an entire structure. Residents may see City representatives conducting field investigations during the design phase. The design and field investigations commenced in early 2024. Construction is planned for 2026 and 2027 subject to council approval. The rehabilitation program includes the following structures:
View map of proposed culverts and bridges For more information, please contact the project team: Hermie Cheung, Project Manager, hermie.cheung@richmondhill.ca | T: 905-771-9996, 5561 Sebouh Apigian, Project Manager, Sebouh.apigian@richmondhill.ca | T: 905-747-6342 |
Stormwater Management Facilities
| Driftwood Pond Retrofit |
|
The City is undertaking the detailed design for the retrofit of Driftwood Pond Stormwater Management Facility (SWMF 8-2), located in Oak Ridges between Bond Crescent/Newbridge Avenue and Timber Valley Avenue. The scope of work includes the retrofit of the existing pond to single-cell dry pond, replacement of headwalls and outlet control structure, installation of oil-grit-separator and landscaping restoration within the pond block. Construction is planned for 2027, subject to future budget approval. For more information, email Project Manager, Sebouh Apigian or call him at 905-747-6342. |
|
Newman Pond Improvements |
|
The City is undertaking the detailed design for upgrades and improvements of the Newman Pond Stormwater Management Facility SWMF 2-11, located on the north side of Newman Avenue to the south and east of residences along Pagoda Drive. The works will address issues related to extended detention, quantity and quality control and phosphorus treatment. Construction is scheduled for 2027, subject to future budget approval. For more information, email Project Manager, Amchan Natkunarajah or call him at 905-771-9996. |
Community Centres and Other Buildings
| Richvale Community Centre: Program Space Repurposing |
|
The City is renewing the former daycare space at Richvale Community Centre by reconfiguring the layout, updating interior finishes, and upgrading building systems. The construction is anticipated to take place during fall/winter 2026.
For more information, email Project Manager, Aimee Tsang or call her at 905-771-9996, ext. 6586.
|
| Bayview Hill Community Centre: Roof Replacement |
|
The City is replacing the skylights and various roof sections at the Bayview Hill Community Centre. Construction is in progress and anticipated to be completed in summer 2026. For more information, email Project Manager, Teresa Chee or call her at 905-771-9996, ext. 6522. |
| M.L. McConaghy Seniors' Centre: Reception Area Renovation |
|
The City is renovating the M.L. McConaghy Seniors' Centre reception area, moving the desk to the lower level to improve services. Construction is scheduled to start in summer 2025 and is expected to be substantially completed by spring 2026. For more information, email Project Manager, Andrew Beshay or call him at 905-771-9996, ext. 5502. |
| Central Library: Interior Renovations |
|
The City is undertaking interior renovations at the Central Library, including flooring replacements, interior finishes, additional electrical infrastructure, and also renovating the Third Floor North Reading Room into a new space. Construction is anticipated to commence in the summer of 2026. For more information, email Project Manager, Alice Wong or call her at 905-771-9996 ext. 6386.
|
| Old Post Office: Cultural Centre Improvements |
| The City is renovating the basement of the Old Post Office to establish occupancy and provide additional program space for cultural activities. Construction is anticipated to commence in the late summer of 2026.
For more information, email Project Manager, Alice Wong or call her at 905-771-9996 ext. 6386. |
| Bond Lake Arena: Spectator Seating Replacement |
| The City is replacing the spectator seating at Bond Lake Arena. Construction is anticipated to commence in the late spring of 2026 and be completed by the end of summer 2026.
For more information, email Project Manager, Alice Wong or call her at 905-771-9996 ext. 6386. |
| Richmond Green Sports Dome: Air Conditioning Installation |
| The City is improving the Richmond Green Sports Dome by installing a new air‑conditioning system to enhance year‑round comfort and humidity control. The construction is anticipated to be completed by spring 2026.
For more information, email Project Manager, Andrew Beshay or call him at 905-771-9996, ext. 5502. |
| New Satellite Operation Yard |
|
The City is renovating the Connor Facility at 39 King Road to create a New Satellite Operations Yard that will better support services in the northern part of the community. The construction is anticipated to be completed by fall 2026. For more information, email Project Manager, Andrew Beshay or call him at 905-771-9996, ext. 5502. |
